IT Leadership Banner and Tagline 

Tool Version Inventory 2.x 

Project Delivery Framework logo

This Tool Version Inventory identifies tool version information in relation to the Texas Project Delivery Framework version 2.x. For a snapshot of tool versions corresponding to Framework 1.0 through 1.9, refer to Tool Version Inventory 1.x. Also see Framework Version History.

Tool Release Date Version

Business Justification Review Gate

Business Case 2.1 31-Dec-2012 2.7
Business Case 2.0 18-Nov-2011 2.6
Business Case 1.9 21-Dec-2010 2.5
Business Case 1.8 30-Jun-2009 2.2
Business Case 1.7 31-Jan-2008 2.0
Business Case Checklist 1.0 31-Dec-2012 2.7
Business Case Workbook Checklist 1.0 31-Dec-2012 2.7
Statewide Impact Analysis 1.6 31-Dec-2012 2.7
Statewide Impact Analysis 1.5 18-Nov-2011 2.6
Statewide Impact Analysis 1.4 21-Dec-2010 2.5
Statewide Impact Analysis 1.3 30-May-2008 2.0
Project Charter 1.6  31-Dec-2012 2.7
Project Charter 1.5 23-Dec-2009  2.3 
Project Charter 1.4 30-May-2008 2.0
Review Gate Approval 1.4 31-Dec-2012 2.7
Review Gate Approval 1.3 30-May-2008 2.0

Project Planning Review Gate

Project Plan 2.4 31-Dec-2012 2.7
Project Plan 2.3 30-Jun-2010 2.4
Project Plan 2.2 23-Dec-2009  2.3 
Project Plan 2.1 30-Jun-2009 2.2
Project Plan 2.0 30-May-2008 2.0
Communication Management Plan – Separate plan (tool) eliminated in Framework 2.0
Configuration Management Plan – Separate plan (tool) eliminated in Framework 2.0
Performance Management Plan – Separate plan (tool) eliminated in Framework 2.0
Risk Management Plan – Separate plan (tool) eliminated in
Framework 2.0
Monitoring Report 1.8  31-Dec-2012 2.7
Monitoring Report 1.7 18-Nov-2011 2.6
Monitoring Report 1.6 30-Jun-2009 2.2
Monitoring Report 1.5 31-Oct-2008 2.1
Monitoring Report 1.4 30-May-2008 2.0
Review Gate Approval 1.4  31-Dec-2012 2.7
Review Gate Approval 1.3 30-May-2008 2.0

Solicitation and Contracting Review Gate

Acquisition Plan 1.9 31-Dec-2012 2.7
Acquisition Plan 1.8 21-Dec-2010 2.5
Acquisition Plan 1.7 30-Jun-2010 2.4
Acquisition Plan 1.6 23-Dec-2009  2.3 
Acquisition Plan 1.5 30-May-2008 2.0
Contract Amendment and Change Order Approval 1.8 31-Dec-2012 2.7
Contract Amendment and Change Order Approval 1.7 21-Dec-2010 2.5
Contract Amendment and Change Order Approval 1.6 31-Oct-2008 2.1
Contract Amendment and Change Order Approval 1.5 30-May-2008 2.0
Review Gate Approval 1.4  31-Dec-2012 2.7
Review Gate Approval 1.3 30-May-2008 2.0

Project Implementation Review Gate

Acceptance to Deploy 1.3 31-Dec-2012 2.7
Acceptance to Deploy 1.2 28-Sep-2007 2.0
Project Closeout Report 1.5  31-Dec-2012 2.7
Project Closeout Report 1.4 30-May-2008 2.0
Review Gate Approval 1.4  31-Dec-2012 2.7
Review Gate Approval 1.3 30-May-2008 2.0

Benefits Realization Review Gate

Post-implementation Review of Business Outcomes 1.6  31-Dec-2012 2.7
Post-implementation Review of Business Outcomes 1.5 18-Nov-2011 2.6
Post-implementation Review of Business Outcomes 1.4 31-Oct-2008 2.1
Post-implementation Review of Business Outcomes 1.3 30-May-2008 2.0
Review Gate Approval 1.4 31-Dec-2012 2.7
Review Gate Approval 1.3 30-May-2008 2.0

For more information about the Texas Project Delivery Framework, contact projectdelivery@dir.texas.gov.